CR Details
CR ID
CR-2024-087
Type
Scope Change
Status
Under Review
Submitted
2024-01-15
Review Started
2024-01-16
Timeline Impact
+1–2 weeks
Budget Impact Summary (Pool-Based)
Modelling
Current: 120h
Change: +10h
New Total: 130h
Coordination
Current: 80h
Change: +5h
New Total: 85h
Impact Tasks (4)
| Description | Affected Scope | Hours |
|---|---|---|
| Expand data model for additional structural loads | TSK-42: Foundation Analysis | +5h |
| Add validation layer for wind load calculations | TSK-47: Wind Load Analysis | +3h |
| Update facade coordination drawings | TSK-44: Facade Modelling | +4h |
| QC review of expanded scope | TSK-45: QC Review Batch | +2h |
Notes
Scope expansion requires additional structural analysis for the extended marina pier section. Client has approved preliminary budget adjustment. Impact on timeline is estimated at 1-2 weeks. All affected teams have been notified.
Moved to Under Review. Budget impact across all pools looks reasonable. Awaiting PL sign-off before final approval.