CR-2024-087: Scope Expansion — Additional Structural Analysis

Created 2024-01-15
Created By Jane Smith
Priority ● P2 — Medium
Total Impact +17h
Overview
Timeline
People

CR Details

CR ID CR-2024-087
Type Scope Change
Status Under Review
Submitted 2024-01-15
Review Started 2024-01-16
Timeline Impact +1–2 weeks

Budget Impact Summary (Pool-Based)

Modelling
Current: 120h Change: +10h New Total: 130h
Coordination
Current: 80h Change: +5h New Total: 85h

Impact Tasks (4)

Description Affected Scope Hours
Expand data model for additional structural loads TSK-42: Foundation Analysis +5h
Add validation layer for wind load calculations TSK-47: Wind Load Analysis +3h
Update facade coordination drawings TSK-44: Facade Modelling +4h
QC review of expanded scope TSK-45: QC Review Batch +2h

Notes

Jane Smith · 2024-01-15
Scope expansion requires additional structural analysis for the extended marina pier section. Client has approved preliminary budget adjustment. Impact on timeline is estimated at 1-2 weeks. All affected teams have been notified.
Admin User · 2024-01-16
Moved to Under Review. Budget impact across all pools looks reasonable. Awaiting PL sign-off before final approval.