Office Tower A — Parameters & Assignment
Rev 2 — View History
Deliverable Selection
Manual Entries (Custom Requirements)
Estimation Parameters
| Sheet Size | Level 1 | Level 2 | Level 3 |
|---|---|---|---|
| A0 | |||
| A1 |
| Sheet Size | Level 1 | Level 2 | Level 3 |
|---|---|---|---|
| A0 | |||
| A1 |
Calculation Mode
Man-months = LOD 400 Total × 5% = 0.15
Inherited from LOD 400
Calculation Mode
Man-months = LOD 400 Total × 3% = 0.09
Calculation Mode
Man-months = LOD 400 Total × 4% = 0.12
Inherited from LOD 400
Inherited from LOD 400
Inherited from LOD 400
Calculation Mode
Man-months = LOD 400 Total × 5% = 0.15
Estimation Summary
Man-months (Modeler)
3.0
Man-months (Coordinator)
1.5
Total Man-months
4.5
Modeler + Coordinator
Total Price
$12,300
Modeler + Coordinator
Sheets / Man-month
10.0
45 sheets ÷ 4.5 MM
Avg Hours / Sheet
17.6
Total Sheets
45
Sheet Size
A1
Packages & Sub-Packages
Drag to reorder
| Package | Sub-packages | Sheets | Status | |
|---|---|---|---|---|
| ⠿ | Architecture | Floor Plans, Elevations, Sections, Details | 18 | Active |
| ⠿ | Structure (Concrete) | Foundation, Columns, Beams, Slabs | 12 | Active |
| ⠿ | MEP | HVAC, Electrical, Plumbing, Fire | 15 | Pending |
Engineer Assignment
P1
P2
P3
| Engineer | Active RFQs | Total Sheets | Current Stages |
|---|---|---|---|
| Sarah Johnson | 3 | 147 | LOD 400, QTO, BEP |
| Mike Chen | 2 | 89 | LOD 400, BEP |
| Lisa Rodriguez | 1 | 56 | QTO |
| Amir Patel | 0 | 0 | — |